Skip to main content
DistrictCampusDirectory
CAMPUS

Frequently Asked Questions

We Are LR. Our School. Our Community. Vote on April 5th


FREQUENTLY ASKED QUESTIONS


Have a question you don’t see answered? Submit it HERE!

The current bonds issued do not pay off until 2027 and 2039. The Debt Service Levy of $0.93 must remain the same to continue paying these bonds.

Without the passage of the 2022 No-Tax Increase Bond Referendum, it will take many years to piece together renovations, improvements, additional classroom space, and the addition of the final safe room without the passage of a the bond. The district will do its best to continue to complete small individual projects as current funding allows, but it will not be possible to keep up with student growth without the passage of this referendum.

The next sizable opportunity for a No-Tax Increase Bond Referendum will be available for Phase III in 2027 when those series of bonds are scheduled to pay off and we have recaptured some equity within our 15% capacity. In Missouri, schools are limited to 15% bonding capacity of their current assessed valuation.

There is an example in the FAQs showing the voting record of the past 3 decades. In 1998, $0.29 rolled back, but then in 2002, just 4 years later, the need to add back $0.35 to build a high school due to student growth had to be approved by voters.

We are optimistic that we will be able to keep up with student growth without an additional tax increase in the near future with the current debt service levy of $0.93.

 

A bond is authorization for a school district to borrow money and to establish a tax rate to pay off the debt over time.  The bond only pays for capital projects, such as facilities and equipment, and may not be used for regular operational costs like salaries or supplies.

A 4/7 majority, or 57.1% plus 1 vote is required to pass a bond issue.

This is possible thanks to good fiscal management by the district. Due to refinancing and paying off some debt early, $32 Million in bonding capacity is available to reissue to complete Phase II improvements and expansions needed. 

$0.93 of the current tax levy is allocated to pay off existing bonds. This debt service levy has remained very consistent for the past 15 years, ranging between $0.86 – $0.97 since 2005.

 

Since 2017, the District has held multiple open community conversations, surveyed stakeholders, held board of education study sessions, and conducted demographic studies. The list of projects were broken into two (2) phases. The determination based on these conversations were that Phase I priorities would include; district-wide safety and security improvements as a top priority, Logan Elementary needing updated, the Upper Elementary Entrance needing updated, and deferred maintenance for safety/security and accessibility and efficiency is necessary. Phase II would happen in 2022 when more bonding capacity was available. Phase II priorities have always been on the list of proposed projects. As we continue to grow as a school district, more classroom space is needed and aging facilities need updating. Improvements and additional facilities are needed to support program offerings, athletics, and activities.

Work would begin immediately on projects that could be completed during the summer of 2022 in order to avoid disruptions during the school year and protect the educational environment as much as possible. Work will continue throughout the 2022 – 2025 school years. Barring any delays in product, shipping, and worker shortages, all projects are expected to be complete during summer of 2025 in time for school to start in August 2025.

History of Current LR Facilities

History of Current LR Facilities

Progress as Promised! Our School. Our Community.

 

We are proud to say that ALL projects promised with the passage of the 2019 bond have been COMPLETED! 


District Safety Measures/Safe and Secure Entrances
Each school’s entrance was reconfigured to allow parents and patrons to interact with the office, but not have access to enter the other parts of the school without permission.

  Upper Elementary Enterance LRHS Secure Entrance LR Primary Secure Entrance LRMS Secure Entrance Elementary

 

Communication & Monitoring Access Upgrades
Upgrades and additions were made in the following areas: security cameras, door access controls, intercom and radio systems, law enforcement notification systems, lighting, fencing, and vehicle/student safety improvements.

Logan Elementary (grades 2-3) Phase I Improvements
The Library was relocated to a new space with the computer lab incorporated into the new Library as a Learning Commons. The old library and computer lab were remodeled to classroom spaces. Music and Art were relocated to a more central location and their former spaces converted back to classrooms. The office was moved to the center-front of the school to create a safe and secure entrance with better visitor parking and improved drop off and pick-up traffic flow. A safe room, built to FEMA standards, was added. This allowed the former “gymnacafetorium” to be utilized as a cafeteria and the new safe room as a gymnasium. Roof replacement, single pane glass replacement, third phase of power additions, lagoon relocation, and improved tracking flow and parking are all projects that were completed as well. In addition to the original projects, the kitchen was able to receive a full renovation.

LRE Library and Computer Lab LRE Learning Commons LRE Art Room

LRE Learning Commons LRE Kitchen  LRE Gym

 

Add Cameras to All School Buses
Before Phase I of the bond was passed, only 19 of 30 school buses had cameras. Now, all regularly driven buses are equipped with cameras.

Athletic Facilities Requiring Safety Improvements
The baseball infield wooden light poles, that were 30+ years old and no one would work on because of their poor condition, have now been replaced. New seating and accessible sidewalks were completed at the baseball and soccer fields. The Middle School Gym bleachers that were non-functioning and beyond repair were replaced. The set of bleachers between the gym and small gym were removed and that space was made more functional for multiple physical education classes to use the spaces at the same time. 

LRMS Gym LRMS Gym LRMS Gym 

LRMS Gym

 

Realtors agree a good school system attracts buyers to an area. Many home buyers ask about the school district before making a decision. In addition, companies that are considering locations for new businesses insist on a good educational system for their children and their employees' children. Knowing the Logan-Rogersville School District has excellent faculty and staff, as well as safe and modern facilities, could be the deciding factor for many families and businesses to come to the community. This would lead to higher property values for homeowners. 

The demographic studies completed in 2015 and again in 2018 did not indicate an immediate need for additional school buildings in Phase I - 2019.

The demographic study conducted prior to the High School opening in 2005 and the Primary School in Jamestown opening in 2008, predicted a steep incline in student growth and the need for additional land purchase and plans for an additional elementary school, additions to existing facilities, etc. However, the financial crisis of 2008, all but stopped LR’s growth. The Department of Elementary and Secondary Education (DESE) enrollment reports show three (3) more LR students in 2015 compared to 2008.

In 2015, the district conducted an in-depth demographic study. The predicted student growth was slow and gradual. The district updated the demographic study in 2018. The 2018 updated study predicted the student growth to continue, but the rate of growth was adjusted downward based on the past three years data.

Not all new housing brings new students to LR. The national average is 0.40 students per new single-family home. The 2021 demographic study predicts there will be 0.5 school age children per each new single-family home built.

The school nearest capacity is Logan Elementary. The other schools have some available room for student growth based on the 2021 demographic study predictions, but not enough to sustain our current pace of growth. Therefore, the addition of classrooms at the current schools is being included in Phase II – 2022.

Local dollars are a larger percentage of LR’s overall revenue than State dollars, so it is important that our local assessed valuation supports public schools (see chart below). While every home built does bring value to LR assessed valuation, property is assessed differently. Agriculture land is assessed at 12%, residential at 19%, and commercial at 31%. The assessed valuation of the LR district has experienced a reboot since the recession. The new norm is much lower than 12+ years ago.

      Assessed Valuation - % Increase

Fund balance is expressed as “Unrestricted Fund Balance.” This is the amount of money you have in reserves. The health and wellness of a district’s finances can be seen in the fund balance maintained over time. Typically, districts will try to hold three (3) months worth of expenses in reserves in case the state has to withhold funds. Fund Balances can also be allowed to increase over a few years in preparation for a large, one-time expenditure, i.e. saving up to build a new FEMA structure. 

Districts have different tolerance levels and ideology regarding fund balances. The more heavily dependent upon State funding, the more likely a school is to have a larger fund balance. The LR Board of Education’s goal is to maintain a fund balance of over 18%.

The chart below shows the fund balance history over the past 18 years. *Note: LR’s fund balances dropped dangerously low during 2008 - 2010. At the time, when a district reached 5%, they were considered a financially stricken district and parents would have had the option to send their students to a neighboring district at LR’s expense. Due to LR’s strong financial management under the current administration and board of education, the LR District’s Standard and Poor’s Rating improved from a “Strong Capacity to Repay Loans” A+ rating, to a AA- “Very High Capacity to Repay Loans” in 2019.

Fund Balance History

 

 

The determination to allocate Phase I, $8,000,000 on safety and security was top priority. It was also determined that accessibility improvements needed to be made to several athletic facilities. There was no sidewalk to the soccer field, nor a wheelchair accessible place to view a soccer game. The same was true for the baseball field. Both facilities needed bleacher improvements while dirt work was being performed for sidewalks. Also, the baseball infield light poles were 30+ years old and no electrical company would work on them due to the age and deterioration of the poles. They had to be replaced. The final athletic project that needed improvements due to safety concerns and accessibility was the Middle School gym. The railing was not to current code, the bleachers were non-functioning and beyond repair, and the chair backs and stairwells needed improvements.

For Phase II, yes, there will be continued improvement to athletic facilities, including additions. The ability for all students to have access to spaces that will allow them to practice and improve is important to their overall development. LR is in need of indoor and outdoor spaces that will be more accessible in inclement weather and in different seasons. Improvements and additions specific to high school activities and athletics spaces will be programmed into the school day to allow students to access new and improved spaces before, during, and after school. 

The Logan-Rogersville School District is pleased to provide revenues and expenditures through the Accountability Portal on the district website. There you will find general information about revenues and expenditures that is shared in an effort to keep all parents and citizens up to date on our financial positions. 

DESE uses the term “Per Pupil Expenditure” (PPE) to express a districts total budget spent per student. The national average is over $12,000. In Missouri, depending on where you live PPE can range from $6,000 to $18,000. The chart below show’s 2021’s PPE for LR and some surrounding schools. 

 

Per Pupil Expenditure 2020-2021

The LR school board commissions an independent audit every single year. LR complies with state statue 165.121 RSMo and submits the audit to DESE (Department of Elementary and Secondary Education). The audit finds are published in the Marshfield Mail according to RSMo 165.121.5(3) requirement to make the audit public information. LR goes above and beyond by publishing all prior year audits to the district website. The audits have all indicated that the financial statement disclosures are neutral, consistent, and clear. To translate audit terms...LR has excellent business practices and procedures and is excellent in the way we manage funds.

LINK TO PRIOR YEARS AUDITS

Federal funding for school districts is based on a state formula that encompasses students with disabilities and those who receive free & reduced lunch. Each year, DESE notifies districts of the amount of federal revenue they will receive based on this formula. There is no way to qualify for more federal funds unless the number of students with disabilities or students who receive free & reduced lunch increases. The district does apply for Federal grants for constructing FEMA shelters, which we have utilized for three buildings within the district. 

The actual turf Football / Soccer surface and installation is approximately $750,000. LR's project includes track surface renovation, field event relocations, visitor bleachers, storage, sidewalk, fencing, lighting, etc. The stadium renovation has not been put out to bid, but is estimated at $1.2 million, which is under 4% of the total bond.

The priority list is being developed with the help of community leaders identified by the board of education. Since stadium renovations will not disrupt daily learning activities, we will be able to start right away. The plan is to complete the playing surface by the first home game.

The ROI is only one factor in creating opportunities for our students. Nearly all BIG 8 conference schools have turf stadiums and the large majority of schools in SWMO have multiple turf fields. It is an expectation of our parents and community to have amenities we can all be proud of. The benefits of an all weather surface will positively impact students K-12, for years to come. We want to provide our students with the same opportunities that other schools are providing. The single largest determining factor in economic development of the city of Rogersville and surrounding community is the quality of our school. An all weather playing surface allows for band, physical education, and all sports to be able to practice on an artificial surface when a natural grass/dirt surface is unplayable due to the weather. Athletics and activities are a very small portion of the entire budget, but plays a large role in the development of our youth. There are savings on mowing, treating, watering, striping, but those savings will not pay for the cost of installation of turf over the life of the turf.

Yes, turf and stadium renovations are typically included in bond referendums. Like wifi, cell phones, and 1:1 devices are a part of our everyday world, an all weather surface is the standard in today's society. Our students and coaches are competing against teams who are able to get more practice and game time due to their turf. LR is actually one of the last schools in the BIG 8 conference, COC conference, and Ozark conference to install turf. There are examples of sponsors and advertisement contracts to help offset the cost of turf. The vendors who market those packages and sell the product keep a large portion of the proceeds. LR has chosen to not go the route of sponsorships or advertisement on the playing surface.

 

The actual turf Football / Soccer surface and installation is approximately $750,000. LR's project includes track surface renovation, field event relocations, visitor bleachers, storage, sidewalk, fencing, lighting, etc. The stadium renovation has not been put out to bid, but is estimated at $1.2 million, which is under 4% of the total bond. The allocations have not been determined because none of the projects have been put out to bid. Our Architect and Construction Manager at Risk could determine estimates, but they would be estimates. The Board of Education, Administration, and Key Community Stakeholders are prioritizing the projects. All of these projects were determined prior to the 2019 No-Tax Increase Bond and have remained on the list for Phase II. The Ballot Language determines which projects can be done. Actual bids will determine how far the 32 million will go towards projects. Priority is additional classrooms to accommodate the current student growth and anticipated number of new students based on the high volume of housing being built in Rogersville.

District Calendar

Today's Events

Contact Information


Rogersville , Missouri 65742
Map
Phone: 417-753-2891