Construction Updates
Construction Update Reports

The most recent...
11/21/08

The current Primary School (PreK-1) plans to move into the new building during the month of January or February (2009). Several grades will be moved during the summer before the 2009-2010 school year.

 

Buildings for 2009-2010 school year.

PreK-1 in new building located in Jamestown Center
Grades 2-3 in old Primary building
Grades 4-6 in Upper Elementary
Grades 7-8 in Middle School
Grades 9-12 in High School


5/23/2007
6/18/2007
7/18/2007
8/02/2007
8/24/2007
10/5/2007
11/26/2007
12/05/2007
12/19/2007
1/24/2008
2/20/2008
3/12/2008
3/26/2008
5/7/2008
6/18/2008
7/1/2008
7/16/2008
8/14/2008
10/22/08
11/21/08

New Primary Building Update
Our goal of moving in after break on January 5th is being pushed back to the latter part of January or first part of February. Roads leading to and around the development have been completed. At this point in time the move is contingent on the weather cooperating throughout the coming weeks and our ability to complete concrete work on the outside of the school. We are working diligently on the interior of the building to install remaining technology, wax floors, and clean classrooms. -12/10/2008

 

 

Part of Primary Playground Area

View entire playground

 

 

Updated December 10, 2008

 

 

 

 

 

 

 

 

 

 

 

 

 

 